Friday, January 20, 2012

Eagle Scout 2012!

POTENTIAL EAGLE SCOUT OR VOLUNTEER PROJECTS FOR SPRING 2012

1 – Erosion control structure in small ditch south of creek.

2 – Design and build shelves for storage room inside New Barn.

3 – Plant grass seed along north property line to control erosion.

4 – Plant grass seed in detention pond near creek

5 – Seed or sod area along new concrete driveway to prevent erosion.  Including erosion control mats to protect area before grass gets started.

6 – Design and build new sign for entrance to the Retreat Center.

7 – Build ladder/steps for access to storage area in New Barn.

8- Build bookshelves for New Barn library.

More projects to come and there is always need for service time!

To Do List for Saturday, January 21

To Do List – January 21, 2012

Come out to the Pro Sanctity Center and help!! See the new building in the last stages and have a cup of hot chocolate!

1- Pick up the retaining wall blocks from front lawn and place on pallet by New Shop.

2- Move iron gate from lawn to area behind school bus.

3- Move lumber from rafters inside small red shed to lumber rack inside New Shop.

4- Pick up non rock trash from crushed rock driveway and put in dumpster.

5- Pick up screws, nails and other metal with large magnet all around New Barn and New Shop and put in dumpster.

6- Cut up firewood and pile neatly behind bus.   Place small brush in burn pile area.  Persons doing this must have the approval of Bob Zaruba before using chain saw.

7- Organize excess wood and metal materials behind bus.

8- Clean up meeting room in cabin.

9 – Remove remnants of black silt fence north of Angel Woods and put in dumpster.

10- Rehang gutter on north side of house.

11- Excavate area of new retaining wall to four (4) feet back of the parking lot curb. 

12 – Sweep floor of New Shop.

13 – Repair silt fence along north property line.

14- Pick up dead limbs from Angel Woods and place in burn pile.

15 – Pick up debris from entire property north of creek and place in dumpster.

16 – Water new trees around cabin if air is above freezing and ground is not frozen.

Thursday, January 19, 2012

SATURDAY I could use some help!

My Mother, My Confidence!

January 19, 2012

Regards: Helping to coordinate a service project Saturday, January 21, 2012 from 10:00 to 12:00 noon.

Hi everyone! 

I have been looking around the property and I see there are piles of pavers and bricks that were used for the rose gardens and such, all mixed into the gardens and lawns. When they tore up the property for the roads they tore everything up! There are also sticks and trash all over the property. I would like to get it cleaned up and ready for the early spring planting and gardening and that we would not have to deal with trash and bricks in the gardens. We also will need to do a little clean up in the new building too.

So I put out a note to St. Pat’s and I have about 12 people coming 6 adults and 6 eighth graders (maybe more)! They will come from 10-12 and end at noon with Hot Chocolate!! Is anyone free to help me supervise and assist our volunteers? I need some help coordinating them and making sure we use those two hours and all that man/child power to our best advantage.

We also need help to plan to put in a small retaining wall on the east side of the parking lot in front of the new building! If you have any ideas or think you know how we might do it ourselves before the winter snows melt and the spring rains come down, please tell us!! HELP!! It is steeper then we thought and for sure it will be a muddy mess if we don’t do something soon! Thanks!

May the good Lord and all the garden and lawn Angels be with us! Teresa

 

Monday, December 5, 2011

December Notes

A lot of progess is being made at Pro Sanctity Retreat Center: New barn is closed in with all doors and windows inplace; Some interior painting in progress; New concrete driveway from highway to new barn; temporary heat in place; The Shop has all doors and windows in place.
Should have final electrical power in place soon; new septic system soon weather permitting;
Expect 100% complete Jan-Feb.

Green Team: Need attic insulated in The Shop; Toro Snowblower works fine; Need to install pegboard and hooks in The Shop; Need exterior lighting installed at The Shop; Need to build/install shelving in large storage room in the new barn; a little siding work remains for the house. Bob Zaruba

Wish List:

Sunday, October 30, 2011

Green Team Progress

Leonard Gabriel led the team in getting new siding installed on west side of the house. Looks really nice.

Bob Zaruba will have a team on site Wednesday Nov. 2nd to complete some work on The Shop. Additional help is always welcome. New tools are accumulating in The Shop. A 3 Ring binder will be placed in The Shop to hold all of the new owners manuals.

Wish List: 1-Peg board (2' x 8' or 4' x 8') to hold tools and supplies; 2-Plain hand saw (20 teeth to the inch); 3-Lots of peg board brackets; 4-tool brackets to hold shovels, rakes, weed trimmers on the wall.; 5-shelving for tools and supplies.

Regards
Bob Zaruba

Friday, October 14, 2011

Join us!

The Blue Team meeting will be on Friday, October 21st for a Pot Luck Lunch meeting – 12:00 noon at the Pro Sanctity Retreat Center!

We are gathering cost quotes and planning notes for the North Hill outside the New Barn preparation and we need info of who wants to donate time, labor, plants, ect. for the hill, also a time line needs to be put together.

In addition, we also will plan a Camp Alumni Mother/ Daughter Spring Day of Prayer and Little Flowers for Our Lady…or something like that!

Our Lady’ Garden Hill and Camp Alumni Retreat will grow very well together!

Teresa and Team

PS – Come out to paint New Barn Rooms! Yes, we are at the painting stage today! Join us today, October 14, 2011 or tomorrow! Come anytime!

Wednesday, October 5, 2011

Green Team meets again! October lst

Results of October 1, 2011 Green Team Meeting

1-Teresa has been advised of a web site used as clearing house to find homes for church items such as pews, altars etc.  She will look into it to see if any of our needs for Barn and Chapel can be met here.

2-Leonard Gabriel can provide free interior paint for use by our volunteers to paint offices and multiuse rooms.

3-The Wells family has offered to provide concrete floor sealant at no cost.  Bob/Teresa will ask Chuck Lacey if it is acceptable product and if he willing to use it in the Barn.

4-Bob/Teresa will ask Chuck Lacey if he plans to install a dryer vent in Barn laundry room.

5-The sloped area north of Barn between Barn and Angel Woods will be sown with native grasses, flowers and/or wildflowers.  Teresa will get estimate from vendor to kill off existing grass on the slope.

6-Consider installing small stained glass artwork in some interior walls in the future.  For example, if we name a conference room after St. Joseph, we may want to build a niche in conference room wall, install stained glass and have back lighting.

7-Consider having simple Stations of the Cross placed on walls of east part of Main Room for use when inclement weather prevents use of outdoor stations. (Eagle Scout?)

8-Storage room next to conference rooms is called The Stall.  This room has high ceiling which would allow for installing overhead shelving on East and West walls.  Consider a future project of single shelf about 4 foot wide and 7 feet above floor for storing light weight materials.  (Eagle Scout?)

9-Altar and Ambo for Chapel will most likely come from St. Ann’s (24th and Poppleton, Omaha).   It will be delivered before floor is in place in Chapel.  Bob/Teresa will find out if we should place altar on concrete floor and place tile around it or install floor tile and set altar on tile.  i.e. will tile support weight of altar?   Consider storing altar in The Stall until needed.  Also keep altar on wheels while stored here.

10-Kitchen will have electrical outlets dropped down from ceiling onto each of the two work tables.  Tables will be fixed to the floor, so outlets should be attached to the tables.

11-If any of the Barn utilities include propane we need to decide where to bury the propane tank.  Also should we buy systems that are easily adapted to natural gas in the future?

12-Existing septic system may be due for pumping.  Teresa will schedule pumping and also measure tank volume.

13-Large cross made from utiity poles needs to be set up.  Need to determine appropriate location. (Eagle Scout?)

14-Green Team should plan on finishing siding on house on October 22, 2011.

15-Green Team needs to develop plans for benches, shelving, tools for The Shop.  (Eagle Scout?)

16-Teresa/Jessi will order overhead garage door for The Shop.

17-Ask Chuck Lacey  to install two more electrical outlets in women’s restroom in Barn.